Developing A Project Control Using Lean Construction to Reduce Project Delays: A Case Study of PT Ubinkayu Indonesia

Authors

  • Mahesa Hamisena Institut Teknologi Bandung
  • Akbar Adhi Utama Institut Teknologi Bandung

DOI:

https://doi.org/10.59261/bustechno.v7i4.811

Keywords:

Lean Construction, Project Control Framework, Project Delay, Current Reality Tree (CRT), Analytical Hierarchy Process (AHP), Planning Reliability

Abstract

Background: Project delays remain a major challenge in the construction industry due to their impact on project performance, revenue recognition, and contractual risks. This issue occurred in PT Ubinkayu Indonesia’s Project PRJ-155 in Surabaya, where actual progress reached only 44.24% compared with the planned 100%, resulting in a 55.76% schedule deviation.

Objective: This study aims to identify the root causes of project delays, determine improvement priorities, and develop an integrated Project Control Framework to enhance project performance.

Methods: A mixed-method case study was conducted using the Define–Measure–Analyze (DMA) approach from Lean Six Sigma, combined with Lean Construction principles. Quantitative analysis evaluated project performance indicators, including labor productivity, planning reliability, workflow stability, corrective activities, rework rate, and workforce utilization. Qualitative data were collected through observations, interviews, document reviews, and focus group discussions. A Current Reality Tree (CRT) was applied to analyze causal relationships, while the Analytic Hierarchy Process (AHP) was used to prioritize improvement alternatives.

Results: The study identified the absence of a structured project control mechanism as the main cause of delays, leading to unstable workflows, shifting priorities, excessive workforce movement, corrective activities, and rework. Three improvement initiatives were proposed: Progress-Based Productivity Management, Installation Readiness Gate with Constraint Heatmap Planning, and Progressive Installation Inspection. AHP results showed that Installation Readiness Gate with Constraint Heatmap Planning was the highest-priority initiative.

Conclusion: The proposed framework can improve planning reliability, labor productivity, workflow stability, and project completion efficiency while reducing corrective activities, rework, and financial risks associated with delays.

References

Alarcón, F. J., Calero, M., Martín-Lara, M. Á., & Pérez-Huertas, S. (2024). An Integrated Lean and Six Sigma Framework for Improving Productivity Performance: A Case Study in a Spanish Chemicals Manufacturer. Applied Sciences, 14(23), 10894. https://doi.org/10.3390/app142310894

Architectural Woodwork Institute. (2024). Introduction and foreword: Wood paneling.

Bigwanto, A., Widayati, N., Wibowo, M. A., & Sari, E. M. (2024). Key Performance Indicators (KPI) to Measure Effectiveness of Lean Construction in Indonesian Project. Sustainability, 16(15), 6461. https://doi.org/10.3390/su16156461

Forcael, E., Rodríguez, C., Vargas, S., Álvarez, P., & Ponce, L. (2020). Role of the Owner’s Representative Within the Construction Industry: Case Study of Chile. Iranian Journal of Science and Technology, Transactions of Civil Engineering, 44(1), 197–208. https://doi.org/10.1007/s40996-019-00327-2

Garcés, G., & Peña, C. (2023). A Review on Lean Construction for Construction Project Management. Revista Ingeniería de Construcción, 38(1), 43–60. https://doi.org/10.7764/RIC.00051.21

Ibrahim, A., Zayed, T., & Lafhaj, Z. (2025). Trends and Gaps in Lean Construction Practices for Construction of Megaprojects: A Critical Review. Alexandria Engineering Journal, 118, 174–193. https://doi.org/10.1016/j.aej.2025.01.046

Insights, F. B. (2026). Interior Design Market Size, Share & Industry Analysis. Fortune Business Insights. https://www.fortunebusinessinsights.com/interior-design-market-112750

Insights, G. M. (2025). Green Building Market. Global Market Insights. https://www.gminsights.com/industry-analysis/green-building-market

Intelligence, M. (2025). Indonesia Real Estate Market: Size & Share Analysis. Mordor Intelligence. https://www.mordorintelligence.com/industry-reports/real-estate-market-in-indonesia

Kuo, T., & Chen, M.-H. (2023). On Using Pairwise Comparison in the Analytic Hierarchy Process: Validity Is Goal While Consistency Is Means. Information Sciences, 648, 119630. https://doi.org/10.1016/j.ins.2023.119630

Marinopoulou, E., Tsavdaridis, K. D., & Efthymiou, E. (2022). Modern Design Methods on Optimised Novel Aluminium Profiles. Buildings, 12(11), 1904. https://doi.org/10.3390/buildings12111904

Mohamad, H. M., Mohamad, M. I., Saad, I., Bolong, N., Mustazama, J., & Mohd Razali, S. N. (2021). A Case Study of S-Curve Analysis: Causes, Effects, Tracing and Monitoring Project Extension of Time. Civil Engineering Journal, 7(4), 649–661. https://doi.org/10.28991/cej-2021-03091679

Moradi, S., & Sormunen, P. (2023). Implementing Lean Construction: A Literature Study of Barriers, Enablers, and Implications. Buildings, 13(2), 556. https://doi.org/10.3390/buildings13020556

Nepal, S., Kumar Bhattarai, S., Sukamani, D., & Nepal, S. (2025). Analysis of Causes for Extension of Time in Construction Projects: A Case Study of Kageshwori Manohara Municipality. Kathford Journal of Engineering and Management, 4(1). https://doi.org/10.3126/kjem.v4i1.74707

Pongboonchai-Empla, T., Antony, J., Garza-Reyes, J. A., Komkowski, T., & Tortorella, G. L. (2024). Integration of Industry 4.0 Technologies into Lean Six Sigma DMAIC: A Systematic Review. Production Planning & Control, 35(12), 1403–1428. https://doi.org/10.1080/09537287.2023.2188496

Research, G. V. (2025). Wood and Timber Products Market Size, Share & Trends Analysis Report by Application (Paper, Lumber, Textiles, Bio Chemicals), by Region (North America, Europe, Asia Pacific), and Segment Forecasts, 2025–2030. Grand View Research. https://www.grandviewresearch.com/industry-analysis/wood-timber-products-market-report

Romzi, N. A., & Doh, S. I. (2022). Underlying Causes of Construction Project Delay: A Review. Construction, 2(2), 7–11. https://doi.org/10.15282/construction.v2i2.7775

Saaty, R. W. (1987). The Analytic Hierarchy Process—What It Is and How It Is Used. Mathematical Modelling, 9(3–5), 161–176. https://doi.org/10.1016/0270-0255(87)90473-8

Serpell, A., & Rubio, H. (2023). Evaluating Project Management (PM) Readiness in Construction Companies: Cases from Chile. Procedia Computer Science, 219, 1642–1649. https://doi.org/10.1016/j.procs.2023.01.457

Wresearch. (2022). Indonesia Interior Design Market. Wresearch. https://www.6wresearch.com/industry-report/indonesia-interior-design-market-outlook

Downloads

Published

2026-10-06