Communication Barriers, Project Communication Quality, and Multi-Project Management Effectiveness in Single-Consultant Parallel Construction Supervision: A SEM-PLS and IPMA Approach
DOI:
https://doi.org/10.59261/bustechno.v7i5.840Keywords:
Communication Barriers, IPMA, Multi-Project Management Effectiveness, Project Communication Quality, SEM-PLSAbstract
Background: Managing multiple construction projects under a single construction management consultant requires effective communication and coordination among stakeholders. Communication barriers may reduce project communication quality and multi-project management effectiveness.
Objective: This study aims to identify relevant communication barriers, examine their effects on project communication quality and multi-project management effectiveness, investigate the mediating role of project communication quality, and determine priorities for communication improvement.
Methods: A quantitative approach supported by expert validation was employed. Data were collected from 80 purposively selected respondents across 32 construction projects. Eight communication barrier factors were identified through a literature review and initial expert validation. Data were analyzed using partial least squares structural equation modeling (PLS-SEM) and importance-performance map analysis (IPMA), followed by final expert validation.
Results: Five of the 25 hypotheses were supported. Information Delay (X1) and Communication Media Mismatch (X3) negatively affected Project Communication Quality (β = −0.123, p = 0.045; β = −0.583, p = 0.021). Information Ambiguity/Inaccuracy (X2) negatively affected Multi-Project Management Effectiveness (β = −0.249, p = 0.033). Project Communication Quality positively affected Multi-Project Management Effectiveness (β = 0.807, p = 0.002) and mediated the effect of Information Delay (β = −0.088, p = 0.016).
Conclusion: Project Communication Quality is central to Multi-Project Management Effectiveness. Improvement priorities include strengthening communication quality, reducing information delays and ambiguity, and ensuring the appropriate selection and use of communication media.
References
Ahmed, R., & Jawad, M. (2022). Avoiding or disregarding: Exploring the relationship between scope creep, project complexity, and the success of construction projects. Project Leadership and Society, 3. https://doi.org/10.1016/j.plas.2022.100064
Al-Otaibi, A., Bowan, P. A., Alabdullatief, A., Albaiz, M., & Salah, M. (2025). Barriers to Sustainable Building Project Performance in Developing Countries: A Case of Ghana and the Kingdom of Saudi Arabia. Sustainability (Switzerland), 17(8). https://doi.org/10.3390/su17083539
Althoey, F., Houda, M., Waqar, A., & Nisar, S. (2024). Comprehensive framework for Integrated Construction Platforms (ICP) implementation and its effect on project success. Ain Shams Engineering Journal, 15(12), 103152. https://doi.org/10.1016/j.asej.2024.103152
Amaechi, C. V, Reda, A., Beddu, S. B., Mohamed, D. B., Syamsir, A., Ja’e, I. A., Ullah, S., Xiaopeng, D., Huang, B., Wang, C., & Ju, X. (2025). A systematic literature review on knowledge management for project risk management in construction. Journal of Building Engineering, 114, 114261. https://doi.org/10.1016/j.jobe.2025.114261
Aziz, N. A., Rahim, F. A. M., & Aziz, N. M. (2022). Systematic literature review on communication in construction project management: Issues among project participants. Journal of Surveying, Construction and Property. https://doi.org/10.22452/jscp.sp2022no1.5
Azman, A., Zaitul, Z., & Utama, W. P. (2025). Analysis of project communication factors on the level of project success in Tebo District. Rang Teknik Journal, 8(1).
Bosfield, R., Gibson, G. E. Jr., & Din, Z. U. (2026). Open repository development framework for knowledge sharing: Best practices in the architecture, engineering, and construction industry. International Journal of Construction Management, 26(1), 12–28. https://doi.org/10.1080/15623599.2025.2505687
Damanik, A. D., Lukman, M., & Latupeirissa, J. E. (2021). Analisis faktor komunikasi terhadap tingkat keberhasilan pelaksanaan proyek konstruksi di Kabupaten Raja Ampat. Paulus Civil Engineering Research, 1(1).
Dharmawan, H. (2022). Analisis risiko kecelakaan kerja dengan metode fishbone diagram dan SCAT saat pelaksanaan stern bunker guna meminimalisir kecelakaan kerja di atas kapal MT. B Star.
Hair, J. F., Hult, G. T. M., Ringle, C. M., & Sarstedt, M. (2022). A primer on partial least squares structural equation modeling (PLS-SEM) (3rd ed.). SAGE Publications.
Ibdayanti, D. R. (2023). Kepentingan relatif faktor-faktor integrasi manajemen komunikasi pada proyek konstruksi di Kota Banda Aceh. Jurnal Manajemen Teknologi Sipil (JMTS), 6(1). https://scholar.google.com/scholar?q=%22Kepentingan%20relatif%20faktor-faktor%20integrasi%20manajemen%20komunikasi%20pada%20proyek%20konstruksi%20di%20Kota%20Banda%20Aceh%22
Institute, P. M. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.
Jaya, I., Hasibuan, G. C. R., & Nasution, D. M. (2023). Manajemen komunikasi proyek konstruksi di masa pandemi Covid-19. TEKNIK, 44(1), 112–122. https://doi.org/10.14710/teknik.v44i1.45512
Juhanda, W., Anggitasari, I., Susilowati, & Utaya, O. P. (2026). Pengaruh manajemen komunikasi terhadap kinerja proyek konstruksi pada perusahaan kontraktor di Kota Jambi. Jurnal Riset Rekayasa Sipil, 9(2). https://doi.org/10.20961/jrrs.v9i2.106456
Likita, A. J., Jelodar, M. B., Vishnupriya, V., Olabode, J., & Rotimi, B. (2025). A guideline for BIM and lean integrated construction practice. Smart and Sustainable Built Environment, 14(4), 1264–1291. https://doi.org/10.1108/SASBE-03-2024-0098
Li, Q., Lee, C.-Y., Jin, H., & Chong, H.-Y. (2022). Effects between Information Sharing and Knowledge Formation and Their Impact on Complex Infrastructure Projects’ Performance. Buildings, 12(8), 1201. https://doi.org/10.3390/buildings12081201
Lubis, Z. (2021). The importance of communication management in improving the performance of construction project managers in developing countries. Journal of Southwest Jiaotong University, 56(3), 1–9.
Malik, S., Taqi, M., Martins, M., & Mata, N. (2021). Exploring the relationship between communication and success of construction projects: The mediating role of conflict. Sustainability, 13(8), 4513. https://doi.org/10.3390/su13084513
Manuputty, N. A., & Nursin, A. (2023). The effect of project communications management on multi-project performance. Jurnal Ilmiah ARCEE, 4(1), 9–21. https://doi.org/10.32722/arcee.v4i01.4798
Mareno, R., Oktaviani, C. Z., & Husin, S. (2022). Analisis korelasi faktor komunikasi proyek terhadap pencapaian kinerja waktu di Kota Banda Aceh. Jurnal Arsip Rekayasa Sipil Dan Perencanaan, 5(1).
Muhaemin, A., & Suroso, A. (2025). Analysis of the influence of project communication management on owner decision to improve implementation time performance in high-rise building construction projects. 14(2), 595–605.
Peli, M., Utama, W. P., Jumas, D. Y., Zulherman, Sesmiwati, Ariani, V., Roza, F., & Putranesia, P. (2022). Faktor determinasi komunikasi efektif di proyek konstruksi dari perspektif multiple stakeholders. Jurnal Studi Komunikasi Dan Media, 26(2), 109–122. https://scholar.google.com/scholar?q=%22Faktor%20determinasi%20komunikasi%20efektif%20di%20proyek%20konstruksi%20dari%20perspektif%20multiple%20stakeholders%22
Prasasto, A. R., & Putra, I. N. D. P. (2024). Analisis pengaruh faktor komunikasi terhadap faktor risiko pada proyek konstruksi gedung bertingkat. Al Qalam: Jurnal Ilmiah Keagamaan Dan Kemasyarakatan, 18(5).
Project Management Institute. (2025). The Standard for Project Management and A Guide to the Project Management Body of Knowledge (PMBOK Guide). In Project Management Institute (Vol. 34, Number 03).
Rahimian, A., Hosseini, M. R., Martek, I., Taroun, A., Alvanchi, A., & Odeh, I. (2022). Predicting communication quality in construction projects: A fully-connected deep neural network approach. Automation in Construction, 139, 104268. https://doi.org/10.1016/j.autcon.2022.104268
Riyadi, S., Sutikna, N., & Setiansah, M. (2023). Manajemen komunikasi interpersonal pimpinan dalam membentuk kohesivitas karyawan perusahaan konstruksi Fajar Utama Karya. NIVEDANA: Jurnal Komunikasi Dan Bahasa, 4(1), 161–171. https://doi.org/10.53565/nivedana.v4i1.833
Saputro, M. Y. D. (2024). Analisis kausalitas komunikasi tidak efektif dalam proyek konstruksi dengan pendekatan PLS-SEM. Sistem Infrastruktur Teknik Sipil (SIMTEKS), 4(2), 173–191. https://doi.org/10.32897/simteks.v4i2.3868
Soomro, M. A., Ali, A., Memon, A. H., Khahro, S. H., & Memon, Z. A. (2024). Improving innovation in construction projects: Knowledge-sharing, open-mindedness and shared leadership. Journal of Innovation & Knowledge, 9(4), 100629. https://doi.org/10.1016/j.jik.2024.100629
Suleiman, A. (2022). Causes and effects of poor communication in the construction industry in the MENA region. Journal of Civil Engineering and Management, 28(5), 365–376. https://doi.org/10.3846/jcem.2022.16728
Susilotomo, F. (2026). The Role of Communication and Stakeholder Management in Reducing Construction Disputes with Trust as an Intervening Variable in Infrastructure Project. Asian Journal of Engineering, Social and Health.
Suwandari, Y. D., & Suratkon, A. (2026). Cash Waqf Financial as a Potential Financial Instrument for Funding Public-Private Partnership (PPP) Infrastructure Projects in Indonesia. International Journal of Sustainable Construction Engineering and Technology, 17(1), 246–259.
Trisnaningati, B. L., Nindya, P., & Aulia, P. L. (2024). Pengaruh komunikasi dalam manajemen proyek. SINTESIA: Jurnal Sistem Dan Teknologi Informasi Indonesia.
Yalçın, G. (2022). The effect of communication on construction project performance: The Turkish construction industry during COVID-19. IAREJ (International Academic Research & Engineering Journal).
Yang, Y., Chen, C., Liu, X., & Zhang, Z. (2025). Integration of Lean Construction and BIM in Sustainable Built Environment: A Review and Future Research Directions. Buildings, 15(14), 2411. https://doi.org/10.3390/buildings15142411
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Caroline Thiovila D A, Yunita Dian Suwandari, Mawardi Amin

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International (CC-BY-SA). that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.